AB748, s. 44 14Section 44. 196.491 (2) (a) (intro.) of the statutes is repealed and recreated to
15read:
AB748,21,1916 196.491 (2) (a) (intro.) The commission shall prepare an annual strategic
17energy assessment that evaluates the adequacy and reliability of the state's current
18and future electrical supply. The strategic energy assessment shall do all of the
19following:
AB748, s. 45 20Section 45. 196.491 (2) (a) 1. and 2. of the statutes are repealed.
AB748, s. 46 21Section 46. 196.491 (2) (a) 3. of the statutes is amended to read:
AB748,22,622 196.491 (2) (a) 3. Identify the location of proposed and alternative specific sites
23for all bulk electric generating facilities and all
and describe large electric generating
24facilities over 200,000 kilowatts for which a certificate of public convenience and
25necessity has not been applied for under sub. (3) but the commencement of whose

1construction is planned within 3 years, or such longer period as the commission
2deems necessary and indicate the impacts of the proposed and alternative
3generating facilities on the environment and the means by which potential adverse
4effects on such values will be avoided or minimized;
on which an electric utility plans
5to commence construction within 3 years and wholesale merchant plants on which
6a person plans to commence construction within 3 years.
AB748, s. 47 7Section 47. 196.491 (2) (a) 3g. of the statutes is created to read:
AB748,22,98 196.491 (2) (a) 3g. Assess the adequacy and reliability of purchased generation
9capacity and energy to serve the needs of the public.
AB748, s. 48 10Section 48. 196.491 (2) (a) 3m. of the statutes is amended to read:
AB748,22,1511 196.491 (2) (a) 3m. Identify the location of tentative and alternative routes for
12and describe high-voltage transmission lines on which an electric utility plans to
13commence
construction is intended to be commenced in the succeeding within 18
14months and indicate the effects of such transmission lines on the environment and
15the means by which potential adverse effects will be avoided or minimized;
.
AB748, s. 49 16Section 49. 196.491 (2) (a) 3r. of the statutes is created to read:
AB748,22,1917 196.491 (2) (a) 3r. Identify and describe any plans for assuring that there is an
18adequate ability to transfer electric power into the state and the transmission area,
19as defined in s. 196.48 (1) (b), in a reliable manner.
AB748, s. 50 20Section 50. 196.491 (2) (a) 4. of the statutes is amended to read:
AB748,22,2221 196.491 (2) (a) 4. Indicate in detail Identify and describe the projected demand
22for electric energy and the basis for determining the projected demand ;.
AB748, s. 51 23Section 51. 196.491 (2) (a) 5. and 6. of the statutes are repealed.
AB748, s. 52 24Section 52. 196.491 (2) (a) 7. of the statutes is amended to read:
AB748,23,2
1196.491 (2) (a) 7. Identify and describe existing and planned programs and
2policies
activities to discourage inefficient and excessive power use; and.
AB748, s. 53 3Section 53. 196.491 (2) (a) 8. of the statutes is repealed.
AB748, s. 54 4Section 54. 196.491 (2) (a) 9. to 13. of the statutes are created to read:
AB748,23,65 196.491 (2) (a) 9. Identify and describe existing and planned generating
6facilities that use renewable sources of energy.
AB748,23,97 10. Consider the public interest in economic development, public health and
8safety, protection of the environment and diversification of sources of energy
9supplies.
AB748,23,1110 11. Assess the extent to which the regional bulk-power market is contributing
11to the adequacy and reliability of the state's electrical supply.
AB748,23,1312 12. Assess the extent to which effective competition is contributing to a reliable,
13low-cost and environmentally sound source of electricity for the public.
AB748,23,1514 13. Assess whether sufficient electric capacity and energy will be available to
15the public at a reasonable price.
AB748, s. 55 16Section 55. 196.491 (2) (ag) of the statutes is created to read:
AB748,23,1917 196.491 (2) (ag) The commission shall promulgate rules that establish
18procedures and requirements for an electric utility to report information that is
19necessary for the commission to prepare strategic energy assessments under par. (a).
AB748, s. 56 20Section 56. 196.491 (2) (am) of the statutes is renumbered 196.491 (2r) and
21amended to read:
AB748,24,222 196.491 (2r) (title) Local ordinances. No local ordinance may prohibit or
23restrict testing activities undertaken by a an electric utility for purposes of preparing
24advance plans or
determining the suitability of a site for the placement of a facility.

1Any local unit of government objecting to such testing may petition the commission
2to impose reasonable restrictions on such activity.
AB748, s. 57 3Section 57. 196.491 (2) (b) (intro.) of the statutes is repealed and recreated to
4read:
AB748,24,75 196.491 (2) (b) (intro.) On or before July 1, the commission shall issue a draft
6of the annual strategic energy assessment that it prepares under par. (a) to each of
7the following:
AB748, s. 58 8Section 58. 196.491 (2) (b) 8. of the statutes is amended to read:
AB748,24,129 196.491 (2) (b) 8. The lower Wisconsin state riverway board if the plan draft
10includes an assessment of the construction, modification or relocation of a
11high-voltage transmission line, as defined in s. 30.40 (3r), that is located in the lower
12Wisconsin riverway as defined in s. 30.40 (15).
AB748, s. 59 13Section 59. 196.491 (2) (b) 9. of the statutes is created to read:
AB748,24,1514 196.491 (2) (b) 9. Each electric utility that is required to report information to
15the commission under the rules promulgated under par. (ag).
AB748, s. 60 16Section 60. 196.491 (2) (c) and (d) of the statutes are repealed.
AB748, s. 61 17Section 61. 196.491 (2) (e) of the statutes is amended to read:
AB748,24,2118 196.491 (2) (e) Any state agency, as defined in s. 16.375 (1), county,
19municipality, town or person may submit written comments on any plan to the
20commission on a strategic energy assessment within 180 90 days after the plan is
21filed
copies of the draft are issued under par. (b).
AB748, s. 62 22Section 62. 196.491 (2) (f) of the statutes is amended to read:
AB748,25,1723 196.491 (2) (f) Because the planning process for facilities siting otherwise
24incorporates consideration and analysis of environmental impact, s.
Section 1.11 (2)
25(c) shall not apply to advance plans a strategic energy assessment prepared under

1par. (a) but the commission shall prepare a single environmental assessment on all
2plans submitted for approval under par. (a)
the strategic energy assessment, which
3shall include a discussion of generic issues related thereto. Such and environmental
4impacts. The commission shall make the environmental
assessment shall be made
5available to the public at least 30 days prior to the hearing under par. (g). The
6assessment on the plans is different from an environmental impact statement on a
7particular facility in that it need not identify the environmental effects of proposed
8sites for facilities in the plan with the same degree of detail as is required when a
9particular facility is considered for a certificate of public convenience and necessity
10under sub. (3). The assessment need not repeat information included in an
11assessment prepared for a plan submitted under par. (a) on a prior reporting date and
12with respect to which no material additional data is required or as to which there has
13been no material change in circumstances. Applicable portions of such assessment
14may be included by reference in any environmental impact statement prepared by
15the commission, including a statement prepared in connection with the
16consideration of an application for a certificate of public convenience and necessity
17under sub. (3).
AB748, s. 63 18Section 63. 196.491 (2) (g) of the statutes, as affected by 1997 Wisconsin Act
1935
, is amended to read:
AB748,26,2020 196.491 (2) (g) Within 180 No sooner than 30 and no later than 90 days after
21the plan is filed copies of the draft are issued under par. (b), the commission shall hold
22a hearing thereon on the draft which may not be a hearing under s. 227.42 or 227.44.
23The hearing shall be held in an administrative district, established by executive
24order 22, issued August 24, 1970, which the commission determines will be
25significantly affected by facilities proposed in the plan to be constructed in the

1following
on which an electric utility plans to commence construction within 3 years.
2The commission may thereafter adjourn the hearing to other locations or may
3conduct the hearing by interactive video conference or other electronic method.
4Notice of such hearing shall be given by class 1 notice, under ch. 985, published in
5the official state newspaper and such other regional papers of general circulation as
6may be designated by the commission. At such hearing the commission shall briefly
7describe the plan strategic energy assessment and give all interested persons an
8opportunity, subject to reasonable limitations on the presentation of repetitious
9material, to express their views on any aspect of the plan. The presentation of such
10views need not be under oath nor subject to cross-examination. The commission
11shall advise all persons present of their right to express their views orally or in
12writing, under oath or otherwise, and of the legal effect of each such form of testimony

13strategic energy assessment. A record of unsworn testimony the hearing shall be
14made and considered by the commission as comments on the plan strategic energy
15assessment
under par. (e). Persons presenting such views shall not be parties. The
16utility, any state agency, county, municipality, town, or any person whose substantial
17rights may be adversely affected by the testing for or construction of facilities
18described in an advance plan, shall, upon filing written notice setting forth its
19interest at least 10 days in advance, be afforded all the rights of a party in a contested
20case.
AB748, s. 64 21Section 64. 196.491 (2) (gm) of the statutes is created to read:
AB748,27,222 196.491 (2) (gm) Based on comments received on a draft, the commission shall
23prepare a final strategic energy assessment within 90 days after a hearing under par.
24(g). The commission shall provide copies of the final strategic energy assessment to

1any state agency, county, municipality, town or other person who submitted
2comments on the draft under par. (e) and to the persons specified in par. (b).
AB748, s. 65 3Section 65. 196.491 (2) (i) to (m) of the statutes are repealed.
AB748, s. 66 4Section 66. 196.491 (2m) (title) of the statutes is repealed.
AB748, s. 67 5Section 67. 196.491 (2m) of the statutes is renumbered 196.491 (3) (a) 3. a. and
6amended to read:
AB748,28,27 196.491 (3) (a) 3. a. At least 120 days prior to the filing of an application for a
8certificate of public convenience and necessity under sub. (3) for a bulk or large
9electric generating facility, the applicant shall notify the department and the
10commission of its intention to make such application and
At the same time that a
11person files an application under subd. 1., the person shall
provide the department
12with an engineering plan showing the location of the facility, a description of the
13facility, including the major components thereof having of the facility that have a
14significant air, water or solid waste pollution potential, and a description of the
15anticipated effects of such the facility on air and water quality. Within 60 30 days
16thereafter after a person provides an engineering plan, the department shall provide
17the applicant person with a listing of each department permit or approval which, on
18the basis of the information contained in the engineering plan, appears to be required
19for the construction or operation of the facility. The department shall, in consultation
20with the commission, also designate which permits and approvals, or portions
21thereof, must be obtained prior to the issuance of the certificate of public convenience
22and necessity. Such designation shall be based on a finding by the department that
23the granting or denial of the same could significantly affect overall facility design or
24location. At any time prior to the issuance of the certificate of public convenience and

1necessity, the department may, in consultation with the commission, waive the
2necessity of obtaining any such permit or approval in advance of such certificate.
AB748, s. 68 3Section 68. 196.491 (3) (a) of the statutes is renumbered 196.491 (3) (a) 1. and
4amended to read:
AB748,28,235 196.491 (3) (a) 1. No person may commence the construction of a facility unless
6such the person has applied for and received a certificate of public convenience and
7necessity from the commission as provided in this section. An application in the form
8and containing the information required by commission rules for such certificate
9shall be filed with the commission not less than 18 months prior to the
10commencement of construction of a bulk electric generating facility, and not less than

116 months prior to the commencement of construction of a large electric generating
12facility or a high-voltage transmission line. Within 10 days after filing the
13application, the commission shall send a copy of the application to the clerk of each
14municipality and town in which the proposed facility is to be located and to the main
15public library in each such county. The applicant shall apply for any permits or
16approvals required by the department prior to the issuance of a certificate of public
17convenience and necessity within 20 days after the application to the commission.
18An applicant shall make a preliminary application for all other permits and
19approvals specified under sub. (2m). Such preliminary application shall be sufficient
20if it identifies the permits and approvals applied for and contains so much of the
21information required for each such permit or approval as is then available to the
22applicant. Thereafter the applicant shall supply necessary additional engineering
23and design information as it becomes available.
AB748, s. 69 24Section 69. 196.491 (3) (a) 2. of the statutes is created to read:
AB748,29,9
1196.491 (3) (a) 2. The commission shall determine whether an application filed
2under subd. 1. is complete and, no later than 30 days after the application is filed,
3notify the applicant about the determination. If the commission determines that the
4application is incomplete, the notice shall state the reason for the determination. An
5applicant may supplement and refile an application that the commission has
6determined to be incomplete. There is no limit on the number of times that an
7applicant may refile an application under this subdivision. If the commission fails
8to determine whether an application is complete within 30 days after the application
9is filed, the application shall be considered to be complete.
AB748, s. 70 10Section 70. 196.491 (3) (a) 3. b. of the statutes is created to read:
AB748,29,2411 196.491 (3) (a) 3. b. Within 20 days after the department provides a listing
12specified in subd. 3. a. to a person, the person shall apply for the permits and
13approvals identified in the listing. The department shall determine whether an
14application under this subd. 3. b. is complete and, no later than 30 days after the
15application is filed, notify the applicant about the determination. If the department
16determines that the application is incomplete, the notice shall state the reason for
17the determination. An applicant may supplement and refile an application that the
18department has determined to be incomplete. There is no limit on the number of
19times that an applicant may refile an application under this subd. 3. b. If the
20department fails to determine whether an application is complete within 30 days
21after the application is filed, the application shall be considered to be complete. The
22department shall complete action on an application under this subd. 3. b. within 90
23days after the date on which the application is determined or considered to be
24complete.
AB748, s. 71 25Section 71. 196.491 (3) (b) of the statutes is amended to read:
AB748,30,4
1196.491 (3) (b) The commission shall hold a public hearing on the an
2application that is determined or considered to be complete in the area affected
3pursuant to s. 227.44. A class 1 notice, under ch. 985, shall be given at least 30 days
4prior to the hearing.
AB748, s. 72 5Section 72. 196.491 (3) (d) (intro.) of the statutes is amended to read:
AB748,30,96 196.491 (3) (d) (intro.) Except as provided under par. (e) and s. 196.493, the
7commission shall approve an application for a certificate of public convenience and
8necessity shall be approved only if the commission determines that all of the
9following
:
AB748, s. 73 10Section 73. 196.491 (3) (d) 1. of the statutes is repealed.
AB748, s. 74 11Section 74. 196.491 (3) (d) 2. of the statutes is amended to read:
AB748,30,1412 196.491 (3) (d) 2. The proposed facility is necessary to satisfy satisfies the
13reasonable needs of the public for an adequate supply of electric energy. This
14subdivision does not apply to a wholesale merchant plant.
AB748, s. 75 15Section 75. 196.491 (3) (d) 7. of the statutes is created to read:
AB748,30,1716 196.491 (3) (d) 7. The proposed facility will not have a material adverse impact
17on competition in the relevant wholesale electric service market.
AB748, s. 76 18Section 76. 196.491 (3) (dm) of the statutes is created to read:
AB748,30,2119 196.491 (3) (dm) In making a determination required under par. (d), the
20commission may not consider a factual conclusion in a strategic energy assessment
21unless the conclusion is independently corroborated in the hearing under par. (b).
AB748, s. 77 22Section 77. 196.491 (3) (e) of the statutes is amended to read:
AB748,31,423 196.491 (3) (e) If the application does not meet the criteria under par. (d), the
24commission shall reject the application or approve the application with such
25modifications as are necessary for an affirmative finding under par. (d). The

1commission may not issue a certificate of public convenience and necessity until the
2department has issued all permits and approvals designated under sub. (2m) as
3necessary prior to the issuance of the certificate of public convenience and necessity

4identified in the listing specified in par. (a) 3. a.
AB748, s. 78 5Section 78. 196.491 (3) (f) and (ff) of the statutes are repealed.
AB748, s. 79 6Section 79. 196.491 (3) (g) (intro.) and 1. of the statutes are consolidated,
7renumbered 196.491 (3) (g) and amended to read:
AB748,31,178 196.491 (3) (g) The commission shall take final action on the an application
9within: 1. 180 days after the application under this subsection for large electric
10generating facilities or high-voltage transmission lines
is determined or considered
11to be complete under par. (a) 2. If the commission fails to take final action within the
12180-day period, the commission is considered to have issued a certificate of public
13convenience and necessity with respect to the application, unless the commission,
14within the 180-day period, petitions the circuit court for Dane County for an
15extension of time for taking final action on the application and the court grants an
16extension. Upon a showing of good cause, the court may extend the 180-day period
17for no more than an additional 180 days
.
AB748, s. 80 18Section 80. 196.491 (3) (g) 2. of the statutes is repealed.
AB748, s. 81 19Section 81. 196.491 (3) (hm) of the statutes is amended to read:
AB748,31,2220 196.491 (3) (hm) The commission and the department shall schedule as many
21hearings under this subsection as practicable at a time and place reasonably
22convenient to the majority of persons in the area of the facility.
AB748, s. 82 23Section 82. 196.491 (3) (j) of the statutes is amended to read:
AB748,32,324 196.491 (3) (j) Any person whose substantial rights may be adversely affected
25or any county, municipality or town having jurisdiction over land affected by an

1advance plan or
a certificate of public convenience and necessity may petition for
2judicial review, under ch. 227, of any decision of the commission regarding the
3advance plan or
the certificate.
AB748, s. 83 4Section 83. 196.491 (3) (k) of the statutes is amended to read:
AB748,32,135 196.491 (3) (k) No person may purchase, or acquire an option to purchase, any
6interest in real property knowing that such property is being purchased to be used
7for the construction of a high-voltage transmission line unless the person gives
8written notice to the prospective seller of the size, maximum voltage and structure
9type of any transmission line planned to be constructed thereon and the electric
10utility by whom it will be operated. Contracts made in violation of this paragraph
11are subject to rescission by the seller at any time prior to the issuance of a certificate
12of public convenience and necessity for the facility high-voltage transmission line by
13the commission.
AB748, s. 84 14Section 84. 196.491 (4) (a) (intro.), 1. and 2. of the statutes, as created by 1997
15Wisconsin Act 27
, are renumbered 196.491 (4) (intro.), (a) and (b), and 196.491 (4)
16(intro.) and (a), as renumbered, are amended to read:
AB748,32,1917 196.491 (4) Exemptions. (intro.) Subsection (2) (3) does not apply to a person
18that constructs, owns or operates electric generating equipment and associated
19facilities if all of the following are satisfied:
AB748,32,2320 (a) The person is not a public utility, a public utility affiliate, an affiliated
21interest
or a cooperative association organized under ch. 185 for the purpose of
22generating, distributing or furnishing electric energy at retail or wholesale to its
23members only.
AB748, s. 85 24Section 85. 196.491 (4) (a) 3. of the statutes is repealed.
AB748, s. 86 25Section 86. 196.491 (4) (b) of the statutes is repealed.
AB748, s. 87
1Section 87. 196.491 (5) of the statutes is created to read:
AB748,33,32 196.491 (5) Large electric generating facility standards. (a) The
3commission shall promulgate rules that establish all of the following:
AB748,33,54 1. Standards for inspecting, maintaining and repairing large electric
5generating facilities that are owned by or provide service to public utilities.
AB748,33,86 2. Standards that the commission determines are necessary for the safe and
7reliable operation of large electric generating facilities that are owned or provide
8service to public utilities.
AB748,33,119 3. Requirements for making annual reports to the commission regarding
10compliance with the standards specified in subds. 1. and 2. The commission shall
11make the reports available for public inspection.
AB748,33,1312 4. Penalties for violating the standards specified in subds. 1. and 2. or the
13requirements specified in subd. 3.
AB748,33,1814 (b) In promulgating rules that establish the standards specified in par. (a) 1.
15and 2., the commission shall consider cost, local geographic and weather conditions,
16electrical industry codes and engineering practices and any other factors that the
17commission determines are related to the safe and reliable operation of the large
18electric generating facilities.
AB748,33,2019 (c) The commission shall conduct periodic investigations to determine
20compliance with the rules promulgated under par. (a).
AB748, s. 88 21Section 88. 196.492 of the statutes is repealed.
Loading...
Loading...